Te Arai Links: A Dream Location, not only for Golfers

Just 75 minutes from Auckland, located on a beautiful white sand New Zealand beach, Te Arai Links is more than just a golf course, it is an extraordinary escape that seamlessly combines world-class golf, luxurious accommodations and eateries, and breathtaking natural landscapes.

Designed by renowned architects Tom Doak, Bill Coore and Ben Crenshaw, Te Arai Links features two 18-hole courses (North Course and South Course). Quickly cementing a reputation as a “golf mecca.”

White Associates played an integral role as the project’s Quantity Surveyor, steering this ambitious vision through some of the most challenging phases.

Our team also provided estimating, procurement advice, and post-contract quantity surveying services to ensure the seamless delivery of standout member facilities, including visitor accommodations, a caddie shack and dining spaces such as the Ocean Restaurant, Ric’s Restaurant, as well as the North Clubhouse.

Photography by: Ricky Robinson, Robinson Studios

Te Arai Links offers luxurious amenities, featuring world-class accommodations, vibrant social spaces, and diverse dining options. Since joining the project in June 2019, White Associates has contributed extensively by cost management, contract administration, and procurement for the development of the accommodation offerings, including: 48 Suites, 19 two-bedroom, Ocean Cottages and 6 four-bedroom Villas.

The members-only Bunker Bar, hidden away in the dunes by the 18th hole of the South Course, is a standout concrete structure buried in sand. Making it the perfect discrete location for thirsty golfers to enjoy a hard-earned drink in view of others completing the final hole.

“Each bespoke build had its own challenges,” notes Matt, Senior Quantity Surveyor at White Associates, “and on top of that there were the universal obstacles caused by building at an isolated location during the COIVD-19 pandemic.”

Working with prominent architects such as Studio John Irving and Chesire Architects, White Associates tackled the cost challenges unique to Te Arai Links’ designs. Procurement was particularly challenging. The semi-rural location made it difficult to attract contractors, especially during a time of heightened global uncertainty. “Finding the right contractors to do this work was quite interesting,” explains Brett Zeiler, Director at White Associates. “We ended up with a mix of commercial contractors and operators with high-end housebuilding experience.”

White Associates carefully managed relationships to ensure every element of the project remained on track, even during lockdowns. “Contract administration was crucial,” adds Sarah Moore, Quantity Surveyor at White Associates. Each build involved different contractors, so maintaining positive relationships was crucial. “Clear communication was key to keeping projects on track and avoiding delays.”

Beyond the golf and luxurious accommodations, Te Arai Links is a conservation success story. Working closely with ecologists, the project has transformed the coastal area into a sanctuary for endangered New Zealand bird species, offering them a safe habitat amid the fairways. Today, native birds nest safely in the dunes, connecting the site’s legacy with its natural roots.

Despite its challenges, Te Arai Links opened in October 2022 as one of the world’s most acclaimed golfing destinations. White Associates’ careful cost management and ability to navigate complexities ensured the project was delivered within budget while reaching the pinnacle of quality.

PROJECT FINANCE QUANTITY SURVEYING INSIGHTS & EDUCATION SERIES

DEVELOPMENT FEASIBILITIES                                                                                         Volume 1

Whilst unpalatable to consider, millions of dollars are wasted yearly by developers completing design and uplifting consents on projects that are simply not feasible. Be it due to infrastructure miscalculation, construction cost underestimation, or land price over-valuation, there is significant scope and nuance in a feasibility, which, if not proficiently completed, will erode a developers margin (and therefore, the funders ‘margin of error’).

To that end, on most occasions, costs could have been saved by taking a little time (and relatively small cost in the scheme of things), to complete a robust development feasibility estimate.

As a quantity surveying firm, we find the initial feasibility stage as an area where we add the most value; by providing a client with accurate information to make the right decision on a particular land holding or proposed development. Despite this, it is not unusual for White Associates to be asked to provide input into the feasibility of a project at a very late stage of pre-construction, oftentimes, even after the approved building consent is obtained. This incurs significant costs for a client in the event desired development margins are not achieved.

A feasibility analysis can be undertaken on relatively limited information, such as a one-page outline of where proposed building costs will sit relative to the project typology, as well as provide a brief outline of building specifications, among other items. This analysis can accordingly be undertaken in a relatively short timeframe, where there are often time constraints.

What does a well-prepared development feasibility look like and include?

The feasibility document would include the potential sales values anticipated after canvasing valuers and local real estate agents, from which the developer will derive an anticipated sales revenue. This is typically undertaken via market comparison valuation processes based on historic, or previous comparable sales achieved. Note that Goods and Services Tax would need to be deducted from the total gross revenue to establish the total revenue value, net of GST.

In addition, the document would include the total cost of the development, considering the land purchase price, existing land holding costs, construction costs, professional fees, local authority fees, marketing fees, sales commissions, finance costs and applicable project contingencies.

The variance between the revenue and total development cost will establish the potential profit/loss for the proposed development, best expressed as a percentage. Each developer will have their own percentage that they would deem acceptable to proceed on, typically based on how robustly/conservatively they believe the feasibility has been prepared.

A historical rule of thumb used to be to only proceed with 30% margin, given it is likely there are potential unforeseen elements which erode the initial margin. Such has not been heeded in recent times, where 20% has been a target, with some proceeding on margins as low as 15%. This margin leaves little margin for error.

How would the construction cost be established in a high-level development feasibility?

To arrive at an overall construction cost for a particular proposed building, a square metre rate for each functional area would be obtained based on the building typology such as industrial, commercial, standalone residential house, terraced housing, apartment etc. A ‘cost per lot’ calculation basis is typically used for residential subdivisions.

For external works, typically a rate per square metre of siteworks area/s would be used, otherwise, an elemental build-up of anticipated construction elements, such as right of ways, carparks landscaping etc, is applied.

The infrastructure services reticulation and drainage potential scope is estimated based on the information available. We often see feasibilities fall short in these cost centres.

From the foregoing, the total construction value will be derived.

What do White Associates look for when we review Borrowers feasibilities?

There are a few key items where we consistently see significant deviations between market pricing and a developers pricing within the various elements of the feasibility:

  • Total RevenueValuers are best placed to establish a reasonable revenue value, however, the key thing we look out for is whether the GST from the proposed sales revenue has been deducted. We have seen this included on various occasions. This distorts the total revenue received which accordingly reduces once the GST is deducted.
  • Construction Costs The square metre rate assigned to the construction works is key, as this will usually be the highest value component in the feasibility.  The difference of omitting a certain element or assigning the wrong rate to a cost centre component can often result in material deviations to actual costs. As quantity surveyors, we benchmark the proposed rate against similar developments.  We will also identify what allowances have been made for civil and siteworks costs, such as driveways and landscaping. Typically, we usually find elements such as fencing and hard landscaping elements, missing, among other bespoke elements not considered, which onerously impact potential development margins.
  • Professional FeesProfessional fees are key in arriving at a total budget figure. These fees are usually benchmarked or calculated as a percentage of the total construction cost. Based on benchmarks of previous projects, this will establish the perceived ‘reasonableness’ of the total fees allowance. Each project will have its own drivers which will influence the fees rendered. Traditionally, consultants’ costs will be in the order of 10% to 18% of the construction costs. Projects which necessitate the most consultants to be engaged, such as apartment projects, will land at the higher end of the range.
  • Local Authority Fees For this component of the feasibility, we look to identify whether development contributions, water infrastructure growth charges, water meter fees, power, water and gas infrastructure costs have been considered, and whether the same are applicable. Another common omission, or where insufficient allowances lie, are for Resource consent, Engineering Plan Approval (EPA) and Building Consent Approval costs. Bonding fees are also a key omission not typically considered. Note that these bonds are typically bonds to Councils for landscaping or maintenance, some of which range in the order of 1.5x the respective construction contract value. In our opinion this would be the “most overlooked” component in the majority of the feasibilities we analyse.
  • Marketing Fees/Sales Commissions For this element we would check to see if a reasonable marketing allowance has been established, which will depend on how extensive the anticipated marketing campaign is proposed to be, and to ensure the sales commissions value has been calculated at a percentage of the total sales revenue. Traditionally, this is circa 2.5% of the gross sales revenue.
  • Finance fees For this component we would ensure brokers fees (if applicable), establishment/ application fees, line fee/s and interest have been considered, of which a finance budget allowance will be derived.
  • Project Contingencies For this component of the feasibility, we would review the value of contingency applied against the type of development, considering the ground risk, site specific risk, building complexity and any other specific risk anticipated for a similar type of project.

What areas in a feasibility do we see Borrowers not given enough consideration?

The main area we commonly see as insufficient is the square metre rate adopted for the build component, which is typically too low in comparison to market pricing. Other areas we see consistent omissions are:

  • Site infrastructure hasn’t been considered comprehensively enough. We have even established drainage upgrades in road corridors and neighbour’s properties upgrades being payable or necessary, which is simply not considered within the feasibility.
  • Power infrastructure costs, such as transformers, etc, do not have sufficient allowance provisioned for.
  • Allowances for LINZ fees, CCTV inspections, and the like have not been provisioned for on subdivision projects.
  • Disbursement and observation costs for architects and structural engineers are not provisioned for where applicable.
  • No contingency allowances have been provisioned for with regard to local authority and consultants’ fees costs.
  • There is not enough consideration given to the legal fees component with allowance required, depending on the project for setting up easements, body corporates, funding legal fees, conveyancing, contract preparation, etc.

Do Civil Works Projects need a Feasibility Review?

As you will be aware, civil engineers are engaged to design and manage the civil works subdivision developments from project inception.  For a land subdivision it is normal for a civil engineer to complete an initial Civil Engineers estimate to establish the potential civil works construction cost for the development.  We would strongly recommend this is thoroughly reviewed by a Quantity Surveyor to ensure all facets of the development have been considered. Traditionally we find there may be significant elements missing in the schedule, which flows through to feasibility omissions, distorting development margins.

What are White Associates observations with regard to feasibilities it currently authors, or peer reviews?

In the current market it is difficult to find developments that have sufficient development margin to progress through to design and construction. The current market conditions would suggest that we are close to entering a time when there will become an equilibrium of all market forces which will work together to create an environment more favourable for development – they are not quite there… yet.

The conditions required to reach the equilibrium are:

  1. Stable and reasonable land prices.
  2. Construction costs in a reasonable and stable space with no or very limited cost escalation.
  3. Interest rates at a reasonable level to limit the impact of finance costs on the overall budget.
  4. House price values increasing.
  5. Housing demand at a strong level.

No international or domestic force majeure events occurring that will affect the New Zealand economy or investment.

For items 1 and 2 these elements have reached a reasonable level with construction costs decreasing in some sectors as a result of the limited construction volume leading to competitive subcontractor pricing.

For item 3, interest rates, this is heading in the right direction, however, there is still a little way to go to reduce the impact of financing costs on development feasibilities and make purchasing a house more affordable for owner occupiers and investors. We currently perceive this as the key hamstring for feasibilities at this current time. We expect this to abate with the OCR reduction currently being canvassed by the RBNZ and the associated effects thereto.

For item 4 there is traditionally a corresponding increase in building asset prices as interest rates decrease, therefore, once the OCR rates decrease, the asset value increase will occur (all things equal). Some pundits have suggested a 1% decrease in interest rates leads to a 10% increase in building asset prices.  Whilst incredibly optimistic and ambitious, time will tell if this will come to fruition in this cycle. What we do know is an increase in house prices will also increase the anticipated development revenue. This will only serve to improve project viability.

For item 5 there still appears to be demand or people that need housing, however, the affordability side affected by interest rates is subduing current demand.

On the basis of the above the factors that need to change are interest rates and housing market inflation The reduction in interest rates will reduce finance costs on feasibilities and stimulate more housing demand.  The house price inflation will create more potential revenue for the proposed development, increasing viability.

What can happen in the real world?

One example that is front in mind is a subdivision project which we became involved with, where circa $3,500,000 of retaining wall and infrastructure costs had not been considered. Such was only identified after a robust feasibility analysis was undertaken by White Associates, and typology changes were therefore affected to ensure the development would still maintain a workable profit margin.

Another example which expounds on the critical nature of the feasibility is on a proposed eight level apartment project, in which we were engaged post building consent uplift and after the tender acceptance of the developer’s preferred contractor. After comparing the expected revenue and considering the proposed budget, we identified that a $3,000,000 loss was expected, prior to the developer even breaking ground. Millions of dollars were spent on going through onerous consenting processes and planning changes, only for the projections to yield a negative return for this developer. Decisions were made accordingly by the developer to divest from the land given the project became unfeasible.

What recommendations would White Associates make…

It is wise to draw as much information as is available at the time of completing the feasibility to make the most informed decision. This would entail obtaining documents such as:

  • The certificate of title.
  • the local Council property file for the property.
  • The Land Information Memorandum (LIM) report.
  • Any geotechnical reports that are available.
  • Any available infrastructure reports.
  • Initial concept design.

Furthermore, engaging with well-established professionals such as an architect/planner that is fully versed on what density you can optimally achieve on a site in the view of any particular site and building restraints. A lawyer to review the title to ensure no encumbrances and other matters also functions as another safeguard.

White Associates encourages Borrowers to engage in the early stages of a project with a quantity surveyor to undertake (or peer review) development feasibilities, to function as another ‘pair of eyes’. This is accordingly necessary given the critical decisions derived from the initial feasibility flow through to the viability and potential profitability for a proposed development.

Potential omissions and inaccuracies determine the fate of a development project.

Disclaimer

The content of this article is general in nature and not intended as a substitute for specific professional
advice on any matter and should not be relied upon for that purpose. It is current as at the date of publication only.

Darin Bayer
Director, Project Finance Representative
dbayer@whiteassociates.co.nz
021 128 7363

Justin Bearne
Associate, Project Finance Representative
jbearne@whiteassociates.co.nz
021 667 551

PROJECT FINANCE QUANTITY SURVEYING INSIGHTS & EDUCATION SERIES

GROUND RISK                                                                                                                      Volume 2

All those familiar with development will be acutely aware that there are a myriad of challenges throughout a project lifecycle that present themselves during a construction project.

One of the more significant challenges that presents itself early in the construction delivery phase is ground conditions, with significant risk associated.

We, accordingly, believe it to be of benefit to canvas this risk item in brief, to ensure ground risk elements do not put a project’s success in jeopardy.

 What Comprises Ground Risk?

  • Underground obstructions
  • Contamination
  • Poor substrate materials such as peat, or material with a propensity for liquefaction
  • High density substrate, such as rock
  • High ground water table
  • Underground streams
  • Steep site inclines with limited stability

Why is it such a risk?

It’s the ‘unknown’ element which creates the risk, as even with geotechnical advice, simply not all ground risk can be identified and quantified. One of the only ways to fully appreciate what the ground beneath a development site is made up of is by completing close proximity investigative boreholes, down a significant depth, over the entire site. As you will appreciate, this can equate to a significant cost. Accordingly, this level of investigation is normally undertaken on larger scale developments, where it would otherwise can be uneconomic to undertake such extensive testing on a smaller scale project.

Traditionally, boreholes and related investigative measures are undertaken only to selected zones of a site, to obtain a high-level understanding of the likely make-up of the substrata of the ground. The results are generally modelled and transposed to all areas of a site, based on a subset of testing.

The main reason why the risk is so great is that the true extent of the grounds geological composition is only established during the excavation of the site, the discovery phase. Traditionally, the project budget is set up prior to this point with only identified risks attracting contingency allowances, without the geological makeup of the site having been fully established and costed. This leaves room for significant cost and programme omissions.

In addition, the risk is heightened by the ground conditions during the various seasons. For example, in winter, the water table of a site may be higher than in the summer months, potentially creating issues on site.

We wish to also note that plant and machinery costs are high, which adds to the cost risk element.

Can it be mitigated or managed?

There are ways to manage ground risk; however, it is extremely difficult to mitigate the risk in a substantial way, bar costing the relative risk accordingly. The key to these costings is the really gaining a comprehensive understanding of what ground conditions that are likely to be encountered. Risk management strategies can be effected, the better this is understood.

As always, the earlier the ground conditions are established, the better that mitigation measures can be effected. For example, there are some development sites where there is substantial risk associated with underground conditions which attracts a cost premium to remediate. This must be considered when negotiating purchase prices for high risk land parcels. Such should be dissuasive for developers to proceed without getting a true handle on geological conditions.

How can it be mitigated or managed?

Management and mitigation techniques are usually focused on having the best understanding possible of the site conditions by conducting a reasonable level of investigation and obtaining the associated reports. Therefore, a geotechnical investigation report with a reasonable volume of borehole investigation and analysis would be obtained. In this report, the groundwater water table height expectations would also be available. Further comprehensive contamination reports would be recommended that look into the background of what the site has been used for to assess risk and undertake testing. Traditionally, we would apportion specific additional contingency budget allowances based on the known risk elements. For example, if there is a certain zone of a site that had a dense rock sub strata we would include an allowance for rock breaking to that zone of the site. Likewise, typically winter works related allowances are made, such as the provision of lime for fill drying, should a larger project be proceeding through winter.

What developments are affected by ground risk more than others?

Traditionally, we find the following developments more susceptible to ground risk:

  • Civil works subdivisions where there is a significant volume of earth being removed
  • Residential sites with poor substrate
  • Sloping sites
  • Sites near rivers, or areas that have a high water table
  • Sites in zones where the ground has a high peat content.
  • Sites near old abattoirs
  • Sites in volcanic rock zones
  • Sites which where industrial chemicals were stored, or services stations
  • Sites that were formally orchards, that may have a high arsenic content in the soil
  • Sites that had old buildings with asbestos content in them that were demolished with potential asbestos contamination in the soil
  • Former landfill sites

What reports are available that review ground elements and what do they cover?

There is a wide range of reports available in the geotechnical investigation field, with the most common reports being:

  • Geotechnical Investigation Report – This report will provide the geotechnical engineers findings after an investigation on the site. The key information that would traditionally be included would be the previous history of the site usage, where the boreholes were taken during the fieldwork completed on the site, what material was found, and general ground condition commentary, as well as the water table level. Suitability of the ground for the proposed building loadings, development/foundation recommendations, among other things, are also found within these reports, which inform potential construction methodology.
  • Contamination Reports – This report would provide a summary of findings with regard to any contamination on the site. The report would highlight the testing area, and what the testing results were. Chemicals that would be traditionally tested for would be pesticides, arsenic, lead, and petrochemicals.
  • Asbestos Reports – This is generally the same as the contamination report above, aside from being asbestos specific
  • Detailed Site Investigation (DSI) Reports – This includes a summary of the geotechnical history to date, site investigation fieldwork results/samples, and sample zones. The report will either state that the soil is in accordance with the residential contaminant standards/ building code standards, or exceeds the standards, with remediation required.
  • Remedial Action Plan (RAP) & Site Management Plan (SMP) – In the event the DSI report noted above results in site soil remediation being required, an RAP and SMP would need to be completed. These reports will provide further testing and detail on what the remediation work will comprise, how it will be undertaken, and what the end results will yield, as well as specific recommendations.
  • Site Validation Report (SVR) – Once the remedial works are completed in accordance with the RAP and SMP noted above, a site validation report will need to be submitted to the relevant local authority that would include further site fieldwork testing confirming the required contamination has been removed, in accordance with the RAP and SMP reports.
  • Groundwater & Dewatering Reports – If there is high groundwater encountered a consent for groundwater take and diversion may be required, therefore further reports may be made available for this scope of work.

How are poor development sites treated, and what are some of the more common remedies?

There are remedies to address problematic sites, with the more common occurrences as follows:

  • Soil Removal – Removal of contaminated earth materials from the site (this may result in additional fill required in the site).
  • Piling – Piles are typically utilised in lieu of significant ground remediation, to transfer the building loads down to where the ground is stable enough to accommodate the load.
  • Palisade Walls – This system is effectively akin to a retaining wall under the ground where either reinforced concrete piles, or timber poles are bored deep into the ground at close centres to stop soil creep on a sloping site. This contains the land within the zone the piles are situated.
  • Shear Keys – This system is used on particularly sloping development sites, where there is risk of a landslide or significant horizontal movement of the ground. The process typically involves the excavation and removal of soils susceptible to movement. The area where the excavated spoil is removed is replaced with suitable fill material, in some instances hardfill, that is compacted. This gives the remedied area more stability during movement events.
  • Dewatering – Where sites have high ground water tables, dewatering could either be undertaken in a simple or more complex fashion, depending on the volume of water that needs to be removed.
  • Pre-Loading – Where the ground would be susceptible to sinking, a common method is placing a dense material, such as Gap 65 basecourse metal (typically used for roading subgrades), in a high stockpile over the affected area, and leaving this for a six-to-twelve-month duration (although, this is project dependent). This slowly compacts the soil to a level where it would be suitable for construction loadings. This is typically used on high concentration peat, low density soils.
  • Mass Concrete filling to voids – Where there is volcanic rock substrata material that has fissures or voids, a typical methodology is filling the voids with a lower strength concrete mixture, which will enable the loads required on the site to be accommodated. There has to be careful consideration on this method as some of the rock caverns can be quite large and mass filling may not be the most cost effective solution.

Does the weather/ seasonal conditions affect a development?

The short answer is yes, sometimes materially.

The summer season, which comprises the earthworks season between 1 October to 30 April of a given year is the time when it is considered the best window to undertake significant earthworks.

When works occur outside of this timeframe, or the summer suffers unseasonal inclement weather events, the impact is usually additional costs. These additional costs will typically comprise:

  • Additional removal of wet or unsuitable materials, resulting in additional excavation and removal of materials off site.
  • Cost associated with drying out of clay materials which can require combining lime with the clay or laying the material in thin layers across the site to dry out sufficiently.
  • Programme delays associated with the inclement weather, where works are unable to be undertaken for a period of time, or when waiting on material to dry.

The above is most applicable to civil works subdivisions on a larger scale; however, can also affect smaller development sites as well, albeit, to a lesser extent.

What does White Associates look for when assessing ground risk?

There are numerous ground risk elements associated with developments which vary, oftentimes significantly, between the North and South Island, between cities, even between suburbs. As a general rule, particular areas are typically well known to have a propensity for a certain risk, such as the volcanic substrata risk in some Auckland Areas, or liquefaction risk in some Christchurch zones.

The information available holds the key to the potential risk associated with a particular development. We would obtain as many reports as we can (which are made available to us) which would normally comprise the geotechnical site investigation report and contamination reports, which sometimes extends to site validation reports, and the like.

In the geotechnical report the findings are key. Typically, we would look at what date the report was completed, how may boreholes were completed (if there are few, this testing may not provide a comprehensive overview of what may be beneath the ground). In addition what the anticipated ground conditions would be, is the groundwater level low enough so it doesn’t create any issues?

Where there is potential risk specifically noted or implied in the geotechnical report, or other pertinent reports, we would include a specific ground risk allowance against that item, which will form a special budget item. For example, in the past we have allowed for rock breaking costs for sites in volcanic rock zones, where it was identified the rock was close to the required excavation level. In addition we have allowed for specific contaminated soil removal where there is a high probability this will occur.

Conclusion

As you will appreciate from the above there are many moving parts associated with ground conditions, that may heighten ground risk for a particular site. The risk can be identified and managed to a point with effective geotechnical consultant input and sufficient soil testing, that captures all areas of the development site.

As with all effective risk mitigants, it is all about obtaining as much information to make an informed decision. Where, for some reason or another, information is not available or is unable to be obtained prior to key decisions being required, the risk needs to be priced the best it can, to assist with any cost impact that may occur as a result of the risk.

In mention of this, ground risk is never able to be fully mitigated, and remains a component of a build project where all parties breathe a sigh of relief once the civil works phase completion milestone of the project has been achieved

Darin Bayer
Director, Project Finance Representative
dbayer@whiteassociates.co.nz
021 128 7363

Justin Bearne
Associate, Project Finance Representative
jbearne@whiteassociates.co.nz
021 667 551

Transforming Nugget Point: Luxury Reimagined

Project Overview

Perched above the scenic Shotover River in Arthur’s Point, Queenstown, Nugget Point Hotel is among the closest accommodations to Coronet Peak ski area and a quick five-minute drive from Queenstown’s lively city centre. Situated near Skippers Canyon and Queenstown Hill, the hotel is renowned for blending serenity with adventure.

The property features more than 40 guest rooms, each with private balconies or patios, alongside a full-service spa, indoor pool, multiple dining spaces, conference facilities, a fitness centre, squash courts, and a private cinema. Known for its unique position, offering exclusive river and mountain vistas over the Shotover river, Nugget Point has long held a prominent place in Queenstown’s hospitality scene. However, it has temporarily closed its doors for an exciting transformation.

A New Era for Nugget Point Hotel

In September 2023, new ownership acquired the property with plans for an extensive refurbishment to elevate it to a five-star plus standard. Scheduled for completion in 2025, the refurbishment will bring a fresh look, a new name, and an updated brand, all aimed at enhancing the Queenstown experience for its guests.

The renovation includes an enhanced lobby and reception area, day spa and a complete refresh of the hotel’s guest rooms and restaurant. The team also plans to add new amenities and broaden service offerings.

Positive Economic Impact

Beyond the aesthetic and functional enhancements, the project is set to boost the local economy, creating jobs and encouraging additional spending in the region. This support helps reinforce Queenstown’s reputation as a world-class travel destination across the luxury accommodation segment.

Key Personnel and Project Team

Key personnel driving this vision include Darin Bayer, Elliot Smith, Syranda Yukel and Jesse Conradie. Collaborating with G2 Studio Limited, the project’s design lead and project manager, and main contractor, Naylor Love Central Otago Limited, the team is working diligently to uphold the highest standards of quality and efficiency.

White Associates’ Role

White Associates has been entrusted with essential roles in this project, providing services in bank funding representation, contract preparation, procurement and construction phase quantity surveying. Since November 2023, we’ve been actively engaged in the pre-construction and procurement phases.

This project marks an exciting new chapter for Nugget Point Hotel. All guest rooms including 37 studios and four one-bedroom suites are being refurbished to a five-star standard. Additional exterior enhancements include fresh façade work, upgraded window joinery, and enhanced balconies with new glass balustrades. Inside, the hotel’s guest rooms, entrance, restaurant, and bar are all being transformed to create a refined and welcoming experience.

For White Associates, this project is a testament to our commitment to delivering exceptional construction services for luxury hotel developments. We look forward to seeing the completed transformation and experiencing the finished product firsthand.

Exploring Heritage and the Treaty: Our Journey to Aotearoa

This week, we continued our journey of deepening our understanding of te reo Māori and the significance of the Treaty of Waitangi. As a team, we took the time to reflect on our diverse backgrounds by sharing our personal stories—where we came from, and how our heritage has influenced our path to Aotearoa.

For some, this was a moment to uncover and share fascinating insights about their lineage, and for others, it sparked a curiosity, inspiring them to dig deeper into their family history and discover more about how their ancestors arriving in New Zealand.

It was a great opportunity to engage in conversation about the Treaty and to start exploring and reflecting on what it means for us all today and what it meant for Māori and non-Māori at the time.

To finish on a fun note, we capped off the session with another lively round of Kahoot, combining learning and enjoyment to reinforce the knowledge we have gained!

Embracing Māori Language Week

Our team engaging in fun activities to embrace Māori Language Week!

The theme for Te Wiki 2024 is ‘Ake Ake Ake – A forever Language’ symbolising resilience, adaptability, and endurance of te reo Māori and the commitment to keeping it thriving for generations to come.

At White Associates, our team came together last week to celebrate Te Wiki by participating in activities that helped us learn and weave te reo Māori into our everyday routines. We’re committed to continuing this journey beyond the week itself, dedicating time in our weekly team meetings to deepen our understanding of te reo Māori and the Treaty of Waitangi, and to embed these learnings into our daily practices.

From Classroom to Construction Site: Adam’s Journey as Quantity Surveyor

While searching for full-time/summer work, Adam discovered White Associates (WA) and was immediately attracted to the diverse projects they offered. Despite his third-year construction degree being in full swing, Adam felt his workload wasn’t challenging enough and thought, why not get a head-start on his career too? This prompted his decision to join the Cadet programme at WA while continuing his full-time studies.

This didn’t come without its challenges, including endless hours spent studying late into the night mixed in with early work mornings. Given the demanding nature of his situation, both he and others had their doubts. Regardless, Adam pushed through and proved everyone wrong. It clearly paid off, as Adam has now moved on from junior quantity surveyor (JQS) to quantity surveyor (QS).

Starting early is really beneficial for your career in the long run, and don’t ever be afraid to jump in and take responsibility.

Challenges aside, he emphasises that there were significant benefits to working and studying simultaneously. “It really helped me grasp the theory a lot better. One day I’d learn the theory at Uni, and the next, I’d be putting it to practice it at work.”

Growing up, Adam always excelled in math and had a quirky habit of spending hours collecting cricket stats. He also took woodworks (a.k.a. construction) in school, which gave him an early introduction to the world of Health & Safety. All this set the stage for his first year at University, where he first encountered quantity surveying – right when it was time to decide his direction in construction.

“The cadetship involved less responsibility and focused more on learning. The exposure was similar to being a JQS, but this time you gradually take on more responsibility, and it’s obviously full-time.” He explains that transitioning from JQS to QS brings continuous added responsibility, more direct communication with various people in the industry (clients, consultants and contractors), and less reliance on associates and senior staff.

Adam enjoys the fun, collaborative environment at White Associates and values the diverse projects he can be a part of, noting how they rapidly enhance his exposure and experience. So far, he’s worked on townhouse developments, prison demolitions, and a data centre. The data centre, in particular, combined with the scale of the project and strict processes that aren’t commonly found in every project.  All of which he views as a significant opportunity for growth.

Outside of Adam’s busy schedule, he continues to indulge in his passion for sports. He is a talented cricket player and has a deep love for watching football, making time for these activities despite his productive work life.

When asked what advice he would give to someone starting their career in quantity surveying, he responds, “if you are in Uni, it is never too early to start your career, if you are prepared to put in the work, then it is never too early.

 

A Journey of Growth: Matt Foxall’s Path to Senior Quantity Surveyor

After exploring Europe in 2018, Matt Foxall directed his career path towards White Associates (WA), inspired by positive reviews from a friend who had previously worked alongside the company. With a Bachelor of Construction majoring in Quantity Surveying from Massey University, coupled with his lasting fascination with cost analysis and his passion for understanding pricing dynamics, he propelled himself into roles focused on post-contracting and estimating within the construction industry.

“Growing up, I was always fascinated with how much things cost and why they cost as much as they did. Getting a better understanding of that now!”

Matt appreciates the variety offered in the role; however, no journey is complete without a few memorable detours. He recalls his unforgettable first week at WA that included a visit to the Christchurch Men’s Prison, “to get to site you had to go into a live prison environment and walk a kilometer or two to the site. And I remember thinking ‘what have I got myself into…?’”. Despite the initial shock, Matt persevered, demonstrating steady growth and dedication to his work.

Recognising Matt’s hard work and contributions, WA recently promoted him to Senior Quantity Surveyor. In this new role, he has embraced more responsibility and leadership while continuing to excel in his field.

With experience spanning both the Contractor and PQS side, Matt has primarily focused on post-contract areas with a sideline in estimating. He now sets his sights on refining his skills in estimating, recognising its pivotal role in his profession. “Now I want to put the majority of my focus and time into estimating to ‘hone’ in on those skills as I think it is an important part of being a quantity surveyor.”

Matt credits much of his career progression to the supportive environment at WAs. “Definitely the biggest attribute to my career development is the support that I get from managers and colleagues. They’ve always got time for me when I come over to their desk or give them a call – even when it feels like a silly question.” This ethos of support and collaboration is integral to the culture at WA, fostering an environment where growth and development thrive.

Matt finds fulfillment in the diverse range of projects he has been a part of. “From my time here, I’ve worked on prisons, high end houses, golf courses, townhouse complexes, data centers and seismic upgrades to name a few”, highlighting the variety that keeps his work engaging and rewarding.

Beyond his successful career as a quantity surveyor, Matt finds passion in activities such as golf, guitar, snowboarding, football, and tennis. He has also achieved success outside of work, as his claim to fame was recording songs at York Street Studios with his mates following a competition win.

Matts’ journey exemplifies not only professional growth but also a commitment to pursuing passions both within and outside the workplace, making him a valued member of the White Associates team.

Stepping into Quantity Surveying: How A Cadetship With White Associates Led to Industry Awards

Connor’s story

Looking back, I could never have imagined I’d end up winning two awards for my research and work, after graduating from Massey University with a Bachelor of Construction. High school wasn’t really for me – I liked math, but not the academic side. After leaving school and working in what I’ll call bridge jobs trying to find a good fit, I worked as a Technical Coordinator for the Auckland Council where I spent most of my time reading plans. I’d always enjoyed construction, and was interested in the construction industry as a whole, so when Covid hit I decided to combine my interests and start studying at Massey University.

Studying during Covid was challenging, especially because it meant you didn’t get to interact with people as usual. The last year was a highlight though, with part of the degree involving real life experience working as a quantity surveyor through a cadetship. I knew of someone in my class who had done their cadetship with White Associates, so I sent them my CV to try my luck. I had an interview and then two weeks later, I started a cadetship with the company.

The role as QS

Starting at White Associates was a bit of a whirlwind, but support from the team meant the transition to a working environment was very smooth. I’ve also greatly appreciated the encouragement and trust when it comes to my work from Richard Moore-Savage, an Associate who also studied at Massey University. His constructive feedback has given me a sense of autonomy, along with learning and developing my skills.

The range of work at our consultancy is fantastic, and since starting I’ve been involved with a range of residential developments and commercial projects.

Because I want to be a cost planner and estimator, it’s been great to have experience in expansions and renovations, as well as new builds. The opportunity to take an estimate from start to finish, as well as working on a wide scope of projects, have definitely been the highlights of my work.

Picking up awards

Winning two awards for my studies was a next-level bonus. It was pretty exciting to have an award presented by the New Zealand Green Building Council for my research. I was selected for this award for the best research around delivering 2030 carbon zero targets, and won a course through the Council. I was also presented with an award by Naylor Love for excellence as a member of the team involved in a BTR project at Sylvia Park.

Having the recognition of peers and mentors in the industry for my hard work as a QS has really been rewarding. I was acknowledged for my teamwork on a project too, because working together and communicating as a team is incredibly important in terms of delivering work on time.

White Associates really cultivate a relaxed and friendly culture where engaging with members of the team becomes second nature. You can sit at the lunch table and talk about anything, even if people are from different teams.

A word from the Managing Director – Konrad Trankels

Connor came to us as a cadet, and immediately fitted right in. He suited the business well in terms of how he worked, his financial understanding and managing his workload. Even though he is new to the industry, he can really contribute to projects because he has great self-learning skills. That’s possibly something that has come from studying during Covid.

Finding someone that both works autonomously, and collaborates well, is rare, especially considering Connor’s age. He is a great string to our bow, as a company taking a fresh approach to construction cost consulting.

The awards Connor’s won are fantastic accolades and are representative of what he’s capable of, and where he’s going in the industry. I’ve sat near Connor when I was in the office and seen how well he collaborates by listening and taking on board important information. His ethics are aligned with the business, and he puts these ethics into his work to provide our clients with the relevant, hard facts related to their projects. He is on the upward trajectory in quantity surveying and the world of business.

Redefining our values to power our future

From White Associates’ very beginning in 2005, our business has been built on a values-based platform. In fact, we established our firm partly to chart a new course from doing things ‘the old way’, which our founders Konrad and Graham saw as ineffective. They were determined to do what they thought was right, more than what was just the norm.

This has been the litmus test for everything that has followed over the next nearly 19 years, as White Associates has grown in sustainable and structured ways while staying true to what matters.

Turning 18 was a big moment for us all at White Associates. As part of our 18th birthday celebrations towards the end of last year, it made sense for us to take time to revisit our values to ensure that they continue to drive us forwards; helping us to operate and deliver systematically in ways that our clients value – and that matter to us.

Amid long discussions, we kept circling back to three core values that are at the heart of what we do, how we do it, and what motivates us. These authentic values, which are already being lived by our team, comprise:

COLLABORATION

To us, collaboration is all about sharing knowledge with each other and our clients to achieve project success together. “Collaboration involves working together to ensure better outcomes through reflection and continuous improvement,” says Justin Maritz, “as well as two-way leadership and 360′ feedback. By seeking perspectives from different departments, roles, companies, and projects, we involve and apply specialist skills collaborating to achieve the best results.”

Justin adds that collaboration is already alive and well within our business. “Not only is it in our departmental and team meetings across the disciplines we practice, but also in our team-wide workshops and how we share information across departments. Mentoring partnerships and cadet Q&A sessions also share knowledge, as do the thought leadership articles, we find, create, and share on social media and internally.”

CONNECTION

This intensely human value is something that really emerged during the Covid years, when we realised how important – and powerful – connection is to each of us as people and in our work to be an effective team. Since then, says Darin Bayer, “understanding the power of connections has enabled our people to embrace flexibility and build strength in our diverse workplace.

“Our culture of autonomy entrusts all team members to enjoy responsibility and take ownership of their work, knowing development and support is available.

“Making this value of connection prominent helps us to support our people in building diverse and long-lasting relationships, as well as empowering strong and trusting work-related connections – in the office and in our industry.”

This value is brought to life within White Associates through opportunities to work across different departments, by being exposed to a variety of projects and clients, as well as at client networking events, which are open to all. We also encourage people to feel accepted, connected and included at work through our Coffee Club, creating lunchtime dining together, and by holding in-house yoga sessions, Friday drinks, and office competitions.

COMMITMENT

“To us commitment is about always putting people first: our team, our clients and our partners,” says Brett Zeiler. “It is about having and showing confidence in our people – their specialist training, team collaboration and support, positivity, communication, and dedication.

“This has the positive flow-on effect of maintaining integrity and following professional, moral ethical standards, and in giving our clients assurance in the quality of our service.

“Our diligent processes and continuous improvement enable us to uphold our good reputation through meeting expectations – of ourselves, our clients, and our project partnerships. It is through our belief and commitment that we continue growing from strength to strength.”

Brett adds that examples of commitment in action start for our people by being available, punctual, and professional. “It is then also about doing what is best for each project, tailoring solutions rather than what is easiest, and always being flexible and responsive to client needs. Then, by investing in relationships and connections we can go beyond expectations, providing solutions outside of scope to help clients navigate their way and succeed.”

Collaboration, connection, commitment. Redefined values that are the best ways of working to keep doing what is right – for our people and our clients, so we all build stronger futures together.